Party wall agreement: when you need one, the notice periods and who pays
Not legal advice. This page has not been reviewed by a solicitor.
The short answer
As of November 2026, in England and Wales you give a neighbour notice under the Party Wall etc. Act 1996 before building on or at the boundary, working on a party wall, or digging near their foundations. Notice is one or two months, depending on the work. A neighbour can consent in writing. If they dissent or do not reply within 14 days, surveyors settle the terms in a party wall award.
Do I need a party wall agreement for a loft conversion?
Only if the work falls within the Act, for example raising or cutting into a party wall, or building on the boundary. GOV.UK lists the examples and says plastering, sockets and drilling for shelves need no notice. Check your plans against the Act, or ask a party wall surveyor.
How much notice do I give a neighbour for party wall work?
Two months for work to an existing party wall. One month for a new wall on the boundary or excavation near a neighbour’s building. GOV.UK says to serve notice between two months and a year before starting. The notice should describe the work.
What happens if my neighbour does not reply to a party wall notice?
An owner who has not consented by notice within 14 days is deemed to have dissented, and a dispute is deemed to exist. GOV.UK says silence cannot be treated as agreement. Surveyors then settle the matter in an award, which sets out the work, the timing and who pays.
Who pays for a party wall agreement?
Usually the building owner pays for the work and, where it is solely for their benefit, usually the neighbour’s surveyor too. The surveyors decide who pays the costs of the award. GOV.UK gives no fee amounts, so ask a surveyor for a written estimate before you appoint one.
Is a party wall agreement the same as a party wall award?
Not quite. The Act’s term is award: a document the surveyors agree setting out the work, how and when it is done, and who pays. Neighbours can instead consent in writing, and GOV.UK says any agreement should be in writing.
What if work starts without a party wall notice?
The GOV.UK booklet says the Act has no enforcement procedure for missing notices, but a neighbour can seek a court injunction to stop the work or other legal redress. Whoever is doing the work still has to avoid unnecessary inconvenience.
Is there a free party wall agreement template?
GOV.UK publishes example letters for party wall notices and replies, with its explanatory booklet. They are for notices, not for the award, which surveyors agree. Notices can go by email only where both sides agree, so check with your neighbour first.
What is a party wall, and is an agreement the same as an award?
GOV.UK describes a party wall as a wall standing on the land of two or more owners, such as a garden wall, or a wall on one owner’s land that two or more owners use to separate their buildings. Wooden fences are not included. A party structure is a floor or other structure that separates buildings or parts of buildings with different owners, such as flats. The rules cover England and Wales, and Scotland differs.
People say “party wall agreement”, but the term in the Party Wall etc. Act 1996 is a party wall award. It is the document surveyors make when owners are in dispute. If the neighbour consents in writing, there is no dispute to settle and no award. GOV.UK also says the Act is separate from planning permission and building regulations approval, so one does not replace the other.
What work needs a party wall notice?
GOV.UK says to tell your neighbour if you plan to do any of three things:
- Build on or at the boundary. Section 1 covers a new wall on the line between two properties, whether it sits astride the line or wholly on your own land.
- Work on an existing party wall or party structure. Section 2 lists the work, including raising or strengthening a party wall, repairing or rebuilding it, cutting into it, and removing chimney breasts or other projections.
- Dig near their foundations. Section 6 applies when you excavate within 3 metres of a neighbour’s building or structure and go deeper than their foundations. It also applies within 6 metres where the excavation would cut a line drawn downward at 45 degrees from the bottom of their foundations.
GOV.UK says minor work needs no notice, such as plastering, adding or replacing electrical wiring or sockets, and drilling to fit shelves or cabinets. The GOV.UK booklet says the test is whether the work could affect the wall’s structural strength or damage the neighbour’s side.
Neighbours cannot stop lawful changes to your property, but they can affect how and when the work is carried out.
How long are the notice periods?
GOV.UK says to give notice between two months and a year before you plan to start, and that the notice should describe the work. Under the Act, a notice lapses if the work has not started within twelve months and is not being pursued diligently.
How can a neighbour respond?
- Consent. The neighbour can agree in writing. For work to an existing party wall, the Act lets the work go ahead without the usual notice process if the adjoining owners and occupiers consent in writing.
- Counter notice. They can ask for extra work to be done at the same time, within one month of the first notice. They pay for that work if it benefits them.
- Dissent. If they refuse, the dispute process starts.
- No reply. An owner who has not consented by notice within 14 days of service is deemed to have dissented, and a dispute is deemed to have arisen. For a new wall on the boundary, consent within 14 days means the wall goes half on each owner’s land, or where they agree. Without it, the building owner can build wholly on their own land.
One agreed surveyor or two?
When there is a dispute, you can agree to appoint one surveyor together, or each appoint your own. The Act provides that two surveyors choose a third to settle any point they cannot agree. Appointments are in writing.
If a neighbour refuses or fails to appoint, the building owner can appoint a surveyor on their behalf. The Act sets ten days from a request for this. You cannot act as your own surveyor.
One agreed surveyor is usually the simpler route, since there is one set of fees and one point of contact. Two surveyors give each owner someone on their side. The sources do not rank the two, so this is a practical judgement, not a rule. The surveyors then make the award, which sets out what work should happen, how and when, and who pays for which part, including surveyors’ fees.
Either owner can appeal an award to a county court within 14 days of receiving it.
Who usually pays the surveyors’ costs?
The general rule is that the building owner pays the expenses of the work. The GOV.UK booklet says that includes the neighbour’s surveyor’s fees where the work is solely for the building owner’s benefit.
There are exceptions. Where repairs are needed because of a defect, the cost is shared in proportion to use and responsibility. Where the neighbour asks for extra work, they pay for it. The reasonable costs of making an award are paid by whoever the surveyors decide. GOV.UK gives no fee amounts, so ask any surveyor for a written fee estimate.
What happens if work starts without notice?
The GOV.UK booklet says the Act has no enforcement procedure for missing notices. A neighbour can instead seek a court injunction to stop the work, or other legal redress. That is where a solicitor can help, because it is a court matter, not a surveyor’s.
Separately, GOV.UK says whoever does the work must avoid unnecessary inconvenience and protect the neighbour’s property, fixing or paying for any damage. Under the Act, the building owner compensates adjoining owners and occupiers for loss or damage caused by work done under it.
Do you need a surveyor or a solicitor?
For most party wall work, a party wall surveyor, not a solicitor, is the professional you need. The surveyors agree the award, and owners can serve notices themselves using GOV.UK’s example letters. Instrukt does not provide surveyors.
A solicitor is useful in other situations: buying or selling a home where party wall work was done or is planned, a dispute that has gone beyond the surveyors, an appeal to the county court, or an injunction. Instrukt is an introducer, not a law firm. We introduce you to an independent, SRA-regulated solicitor, and you decide whether to instruct them. See how introductions work. For the sale or purchase side, the exchange and completion guide shows where your solicitor’s checks fit.
Questions
What is a party wall agreement?
Can a neighbour stop my building work?
Does party wall work need planning permission as well?
Does the Party Wall etc. Act apply in Scotland?
Can I be my own party wall surveyor?
Party wall dispute, or a sale or purchase affected by one?
Tell us about the property and what has happened. We introduce you to an independent, SRA-regulated solicitor, who can explain your options. Instrukt is not a law firm.
Get a solicitor’s quoteSources
- GOV.UK: Party walls and building work
- GOV.UK: Work you must tell your neighbour about
- GOV.UK: When and how to tell your neighbour
- GOV.UK: Reaching an agreement with your neighbours
- GOV.UK: If you cannot agree
- GOV.UK: When works begin
- GOV.UK: Preventing and resolving disputes in relation to party walls (example letters)
- GOV.UK: The Party Wall etc. Act 1996 explanatory booklet
- Party Wall etc. Act 1996 (legislation.gov.uk)
- Party Wall etc. Act 1996, section 1: new building on line of junction
- Party Wall etc. Act 1996, section 2: repair etc. of party wall
- Party Wall etc. Act 1996, section 3: party structure notices
- Party Wall etc. Act 1996, section 4: counter notices
- Party Wall etc. Act 1996, section 5: disputes arising under sections 3 and 4
- Party Wall etc. Act 1996, section 6: adjacent excavation and construction
- Party Wall etc. Act 1996, section 7: compensation
- Party Wall etc. Act 1996, section 10: resolution of disputes
- Party Wall etc. Act 1996, section 11: expenses
This guide is general information, not legal advice. Instrukt is not a law firm.