The short answer
As of October 2026, a dilapidations claim is a landlord’s claim at the end of a business lease in England and Wales for repairs and other work the tenant should have done. Damages for disrepair can’t exceed the fall in the value of the landlord’s interest, under section 18(1) of the Landlord and Tenant Act 1927.
What are dilapidations?
“Dilapidations” covers breaches of the lease obligations about the state of the premises. The Dilapidations Protocol doesn’t define the word, and says the work required depends on the contractual terms of the lease and any other relevant documents. It lists repair, reinstatement and redecoration as categories of breach. At the end of a lease, landlords commonly claim for:
- repairs the tenant was obliged to carry out;
- redecoration, if the lease requires it in the last year or at the end;
- removing the tenant’s alterations and reinstating the original layout, if the lease or a licence requires it;
- consequential losses, which the protocol says the landlord should quantify before issuing proceedings (paragraph 9.1).
What you owe depends on the wording of your lease and any licences (Dilapidations Protocol, paragraph 1.4), so they are the starting point. This guide covers commercial leases in England and Wales.
How does the Dilapidations Protocol work?
The Dilapidations Protocol is a pre-action protocol under the court rules. It sets out the steps landlords and tenants are expected to follow before going to court, and a court can take failure to follow it into account. The usual timetable is:
| Step | Who | Usual timing |
|---|---|---|
| Schedule of dilapidations: each breach, the clause, the remedy and its cost | Landlord | Generally within 56 days after the lease ends |
| Quantified Demand: the sum claimed, with evidence | Landlord | Same timescale as the schedule |
| Response, item by item, endorsed by the tenant or its surveyor | Tenant | Usually within 56 days of the Quantified Demand |
| Without prejudice meeting | Both | Generally within 28 days of the Response |
| Breakdown of loss, based on a diminution valuation or actual spend | Landlord | Before issuing proceedings |
| Tenant’s own diminution valuation, if relied on | Tenant | Generally within 56 days of the landlord’s breakdown |
Under the protocol, the landlord (or its surveyor) endorses the schedule to confirm that full account has been taken of the landlord’s intentions for the property (paragraph 3.6). Before issuing proceedings, the landlord should quantify its loss with a breakdown based on a formal diminution valuation, its actual spending on the works, or both where some work has been done (paragraph 9.1). The parties should also consider alternative dispute resolution, such as mediation (paragraph 8).
What is the section 18(1) cap?
Section 18(1) of the Landlord and Tenant Act 1927 limits damages for breach of a repairing covenant in two ways:
- The diminution cap. Under section 18(1), damages can’t exceed the amount by which the value of the landlord’s interest (the “reversion”) is reduced by the disrepair.
- Demolition or structural alteration. Under section 18(1), no damages are recoverable for failing to leave the premises in repair if, at or shortly after the end of the lease, they are to be demolished or altered so that the repairs would be valueless.
Under section 18(1) of the Landlord and Tenant Act 1927, damages for disrepair can’t exceed the amount by which the disrepair reduces the value of the landlord’s interest, and none are recoverable for failing to leave the premises in repair at the end of the lease if they are to be demolished or altered so that the repairs would be valueless. The example below shows how that cap works.
Worked example (illustrative figures). The landlord’s surveyor costs the repairs at £80,000.
| Scenario | Cost of repairs | Fall in value of the reversion | Maximum repair damages |
|---|---|---|---|
| Landlord re-lets after doing the works; a buyer would knock the full cost off | £80,000 | £80,000 | £80,000 |
| Weak market: a buyer would only knock £50,000 off for the disrepair | £80,000 | £50,000 | £50,000 |
| Landlord is refurbishing so the repairs are wasted | £80,000 | May be little or none | May be little or nothing |
| Building is to be demolished at the end of the lease | £80,000 | Not relevant | Nil (second limb of s18(1)) |
The cap applies to damages for breach of a covenant to keep or put premises in repair. Claims under other clauses, such as removing alterations, aren’t within its wording. Diminution in value is a matter for expert valuation, which is why the protocol asks for a formal valuation where works aren’t going to be done.
How can you keep a dilapidations bill down?
- Before you sign: limit repair to the condition shown in an annexed schedule of condition; check reinstatement obligations in the lease and any licence for alterations.
- During the lease: keep up repairs and keep records, photos and invoices.
- Before you leave: ask the landlord early whether it wants alterations removed, get your own surveyor’s view, and consider doing the work yourself instead of paying damages.
- After a claim arrives: respond within the protocol timetable, ask what the landlord intends to do with the building (the landlord’s schedule must be endorsed to confirm it takes account of those intentions), and challenge items it won’t actually carry out.
Your best protection is in the lease you sign. Have it checked by a solicitor before you sign: we introduce you to an independent SRA-regulated solicitor who can review the repairing and reinstatement clauses.
Questions
What is a dilapidations claim?
How long does a landlord have to serve a schedule of dilapidations?
What is section 18 of the Landlord and Tenant Act 1927?
Can a landlord claim dilapidations if they are knocking the building down?
Should I do the dilapidations work myself before I leave?
Worried about the end-of-lease bill?
Tell us about the lease and we’ll introduce you to an independent SRA-regulated solicitor who can check the repairing and reinstatement clauses before you sign.
Have your repair clauses checkedSources
- Landlord and Tenant Act 1927, section 18
- Ministry of Justice: Pre-Action Protocol for claims for damages in relation to the physical state of commercial property at termination of a tenancy (the Dilapidations Protocol)
- RICS: Code for leasing business premises, England and Wales, 1st edition (Part 3 para 2.4, state of premises after a break)