## The short answer

As of November 2026, the [right to manage](https://www.gov.uk/leasehold-property/right-to-manage-and-management-disputes) lets the leaseholders of a block of flats in England and Wales take over the landlord’s [management functions, such as services, repairs, maintenance and insurance](https://www.legislation.gov.uk/ukpga/2002/15/section/96), through a company they form, without proving bad management. The building needs [at least two flats, and qualifying leaseholders must hold at least two-thirds of them](https://www.legislation.gov.uk/ukpga/2002/15/section/72).

## What is right to manage?

It lets leaseholders take over the landlord’s [functions on services, repairs, maintenance, improvements, insurance and management](https://www.legislation.gov.uk/ukpga/2002/15/section/96) through a company. [GOV.UK says](https://www.gov.uk/leasehold-property/right-to-manage-and-management-disputes) it works without having to prove bad management. You can run the building yourselves or pay a managing agent.

## Does the landlord have to agree to right to manage?

No. A landlord can give a [counter-notice](https://www.legislation.gov.uk/ukpga/2002/15/section/84), but only to admit the company is entitled or to allege, under a named provision of the Act, that it is not. The company then has two months to apply to the tribunal, or [the claim is treated as withdrawn](https://www.legislation.gov.uk/ukpga/2002/15/section/87).

## Which buildings qualify for right to manage?

A [self-contained building, or self-contained part of one, with at least two flats](https://www.legislation.gov.uk/ukpga/2002/15/section/72), where qualifying tenants hold at least two-thirds of the flats. Qualifying tenants have [leases of more than 21 years](https://www.legislation.gov.uk/ukpga/2002/15/section/76). [Schedule 6 excludes](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6) some buildings, such as those over the non-residential limit.

## What is the right to manage process?

Leaseholders [form an RTM company](https://www.legislation.gov.uk/ukpga/2002/15/section/73), [invite the other qualifying tenants to join](https://www.legislation.gov.uk/ukpga/2002/15/section/78), then serve a [claim notice](https://www.legislation.gov.uk/ukpga/2002/15/section/79) at least 14 days later. The landlord has [at least a month to respond](https://www.legislation.gov.uk/ukpga/2002/15/section/80). If undisputed, the company takes over on the [date in the notice](https://www.legislation.gov.uk/ukpga/2002/15/section/90).

## How much does right to manage cost, and who pays the landlord’s costs?

Since 3 March 2025 the company and its members are [not liable for others’ costs of a claim](https://www.legislation.gov.uk/ukpga/2002/15/section/87A), except in set cases such as a tribunal costs order. The [tribunal can order costs](https://www.legislation.gov.uk/ukpga/2002/15/section/87B) where a claim ends after unreasonable conduct. Members agree how to share the company’s own costs.

## Can a right to manage company buy the freehold?

Right to manage covers management, not ownership. If the freehold is transferred to an RTM company, [section 73(5)](https://www.legislation.gov.uk/ukpga/2002/15/section/73) says it stops being an RTM company when the transfer is executed. Buying the freehold is a separate route, covered in our guide to [extending a lease or buying the freehold](https://instrukt.co.uk/guides/lease-extension-vs-buying-the-freehold).

## How many leaseholders have to join the RTM company?

When the claim notice is given, [members must include qualifying tenants of at least half the flats](https://www.legislation.gov.uk/ukpga/2002/15/section/79) in the building. If there are only two qualifying tenants, both must be members. [Members are qualifying tenants](https://www.legislation.gov.uk/ukpga/2002/15/section/74) and, from the acquisition date, landlords under leases of the premises.

## Contents

1. [What does right to manage mean?](#what-is-right-to-manage)
2. [Which buildings qualify?](#which-buildings-qualify)
3. [What are the steps to claim right to manage?](#the-steps)
4. [What happens on the acquisition date?](#after-acquisition)
5. [What does it cost, and who pays the landlord’s costs?](#costs)
6. [What has the Leasehold and Freehold Reform Act 2024 changed?](#2024-act)
7. [When does it help to speak to a solicitor?](#getting-help)
8. [Questions](#questions)

## What does right to manage mean?

Right to manage is a right under [Part 2, Chapter 1 of the Commonhold and Leasehold Reform Act 2002](https://www.legislation.gov.uk/ukpga/2002/15/part/2/chapter/1), which extends to England and Wales. [GOV.UK describes it](https://www.gov.uk/leasehold-property/right-to-manage-and-management-disputes) as letting you and the other leaseholders take over certain management responsibilities from the landlord, without having to prove bad management.

Once the company acquires the right, [the landlord’s management functions under the leases become the company’s instead](https://www.legislation.gov.uk/ukpga/2002/15/section/96). The Act defines management functions as those on services, repairs, maintenance, improvements, insurance and management. It leaves out [functions relating to re-entry or forfeiture](https://www.legislation.gov.uk/ukpga/2002/15/section/96).

[GOV.UK says](https://www.gov.uk/leasehold-property/right-to-manage-and-management-disputes) the leaseholders can manage the building themselves or pay a managing agent. After the right is acquired, the landlord [may not do what has become the company’s function under the lease](https://www.legislation.gov.uk/ukpga/2002/15/section/97), except under an agreement with the company. A landlord [can still insure the premises at its own expense](https://www.legislation.gov.uk/ukpga/2002/15/section/97).

This is not the same as owning the freehold. For that route, see our guide to [extending a lease or buying the freehold](https://instrukt.co.uk/guides/lease-extension-vs-buying-the-freehold).

## Which buildings qualify?

The building must meet each of these tests under [section 72](https://www.legislation.gov.uk/ukpga/2002/15/section/72).

- It is a [self-contained building or a self-contained part of a building](https://www.legislation.gov.uk/ukpga/2002/15/section/72). A building is self-contained if it is structurally detached. A part is self-contained if it is a vertical division that could be redeveloped independently and its pipes, cables and other fixed services are, or could be, provided independently.
- It contains [two or more flats held by qualifying tenants](https://www.legislation.gov.uk/ukpga/2002/15/section/72).
- Flats held by qualifying tenants are [not less than two-thirds of all the flats](https://www.legislation.gov.uk/ukpga/2002/15/section/72) in the premises.

A qualifying tenant is, [in general, the tenant of a flat under a long lease](https://www.legislation.gov.uk/ukpga/2002/15/section/75). A long lease is mainly [one granted for a term of years certain exceeding 21 years](https://www.legislation.gov.uk/ukpga/2002/15/section/76), with some other cases listed in the same section. [A business tenancy protected by Part 2 of the Landlord and Tenant Act 1954 does not count](https://www.legislation.gov.uk/ukpga/2002/15/section/75), and each flat has at most one qualifying tenant at a time. Joint tenants are [treated together as the qualifying tenant](https://www.legislation.gov.uk/ukpga/2002/15/section/75).

These buildings are excluded by [Schedule 6](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6).

- **Too much non-residential space.** [The right does not apply if the internal floor area of the non-residential parts exceeds 50%](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6) of the internal floor area of the premises as a whole. Common parts are not counted as non-residential, and a garage, parking space or storage area used with a particular dwelling is treated as residential. The limit was 25% until 3 March 2025 (see the [2024 Act changes](#2024-act) below).
- **Resident landlord.** [The right does not apply if the premises have a resident landlord and contain no more than four units](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6). Premises have a resident landlord only if they are not, and are not part of, a purpose-built block of flats, and the freeholder or an adult member of the freeholder’s family has lived in a flat as their only or principal home throughout the last twelve months (or, after a recent acquisition, since within 28 days of it, where the premises already had a resident landlord).
- **Council landlord.** [The right does not apply if a local housing authority is the immediate landlord of any qualifying tenant](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6) of a flat in the premises.
- **Different freeholders.** [Where different people own the freehold of different parts, the right does not apply if any of those parts is a self-contained part of a building](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6).

## What are the steps to claim right to manage?

The steps below follow [Part 2, Chapter 1 of the 2002 Act](https://www.legislation.gov.uk/ukpga/2002/15/part/2/chapter/1). Prescribed forms and regulations also apply, so a solicitor can check the notices before anything is served.

1. **Form an RTM company.** [It must be a private company limited by guarantee](https://www.legislation.gov.uk/ukpga/2002/15/section/73), with articles stating that its object, or one of them, is acquiring and exercising the right to manage the premises. There can be only one RTM company for the same premises. Its articles [must be consistent with regulations](https://www.legislation.gov.uk/ukpga/2002/15/section/74) made under the Act.
2. **Get information if you need it.** The company [can give a notice requiring information it reasonably needs for the claim notice, and the recipient must comply within 28 days](https://www.legislation.gov.uk/ukpga/2002/15/section/82).
3. **Send the notice inviting participation.** [The company must give it to every qualifying tenant who is not, and has not agreed to become, a member](https://www.legislation.gov.uk/ukpga/2002/15/section/78). It must state the intention to acquire the right, name the members and invite the recipients to join, and either enclose a copy of the articles or say where they can be inspected and copied.
4. **Wait at least 14 days, then serve the claim notice.** [The claim notice cannot be given until each person owed an invitation has had it at least 14 days before](https://www.legislation.gov.uk/ukpga/2002/15/section/79). At that date the members must include qualifying tenants of at least half the flats, or both qualifying tenants if there are only two. The notice goes to [each landlord, each other party to a lease, and any manager appointed by a tribunal](https://www.legislation.gov.uk/ukpga/2002/15/section/79), and a copy goes to each qualifying tenant.
5. **Set the dates.** [The claim notice must give a counter-notice date not earlier than one month after the notice is given, and an acquisition date at least three months after the counter-notice date](https://www.legislation.gov.uk/ukpga/2002/15/section/80). In effect, an undisputed claim takes at least four months from the date the notice is given.
6. **The landlord may respond with a counter-notice.** [It either admits the company is entitled or alleges that it is not, naming a provision of the Act](https://www.legislation.gov.uk/ukpga/2002/15/section/84). If entitlement is denied, [the company has two months to apply to the tribunal](https://www.legislation.gov.uk/ukpga/2002/15/section/84), and it does not acquire the right unless the tribunal finally decides it was entitled or the landlord agrees in writing.
7. **The acquisition date.** If there is no dispute, [it is the date in the claim notice](https://www.legislation.gov.uk/ukpga/2002/15/section/90). After a tribunal decision becomes final, or a written agreement, [it is three months later](https://www.legislation.gov.uk/ukpga/2002/15/section/90).

Other points in the Act are worth knowing. If a landlord cannot be found, [the company can apply to the tribunal for an order](https://www.legislation.gov.uk/ukpga/2002/15/section/85). The company [can withdraw the claim notice at any time before it acquires the right](https://www.legislation.gov.uk/ukpga/2002/15/section/86). A claim notice is [not invalidated by inaccuracies in the particulars required by section 80](https://www.legislation.gov.uk/ukpga/2002/15/section/81), but that does not make errors safe to ignore, so have the notice checked.

## What happens on the acquisition date?

A landlord, or a manager appointed by the tribunal, [must pay the company the accrued uncommitted service charges it holds](https://www.legislation.gov.uk/ukpga/2002/15/section/94) on the acquisition date, or as soon after as is reasonably practicable. The company or the payer can apply to the tribunal to determine the amount.

Existing management contracts also come into play. [The person who is the manager party to a contract must give notices of it to the contractor and to the company](https://www.legislation.gov.uk/ukpga/2002/15/section/92), so the company learns what contracts exist.

## What does it cost, and who pays the landlord’s costs?

No primary source sets the cost of forming an RTM company, paying a managing agent or instructing a solicitor, so this page gives no figures. Ask each firm for a written quote that says what it covers.

The rules on who pays other people’s costs changed on 3 March 2025. Before then, [section 88 as enacted made an RTM company liable for the reasonable costs a landlord incurred in consequence of a claim notice](https://www.legislation.gov.uk/ukpga/2002/15/section/88/enacted). [Section 88 was omitted from 3 March 2025](https://www.legislation.gov.uk/ukpga/2002/15/section/88), and [section 87A now applies](https://www.legislation.gov.uk/ukpga/2002/15/section/87A).

Under [section 87A](https://www.legislation.gov.uk/ukpga/2002/15/section/87A) and [section 87B](https://www.legislation.gov.uk/ukpga/2002/15/section/87B), as now in force:

- [The company and its members are not liable for costs incurred by any other person in consequence of a claim notice, except as section 87A sets out](https://www.legislation.gov.uk/ukpga/2002/15/section/87A), and a lease or other arrangement that says otherwise has no effect to that extent.
- [They are liable for costs in court or tribunal proceedings only where the court or tribunal has power to order them and does so](https://www.legislation.gov.uk/ukpga/2002/15/section/87A).
- [The tribunal may order the company to pay a landlord’s reasonable costs, incurred outside court or tribunal proceedings, if the claim notice is withdrawn or ceases to have effect and the company acted unreasonably in giving it or not withdrawing it sooner](https://www.legislation.gov.uk/ukpga/2002/15/section/87B). Each current and past member is then also liable, jointly with the company, though [not a member who has assigned their lease to someone who has joined the company](https://www.legislation.gov.uk/ukpga/2002/15/section/87B).
- [The company is liable for the reasonable costs of a person who complies with an information notice](https://www.legislation.gov.uk/ukpga/2002/15/section/82), and the tribunal decides the amount if it is not agreed.
- [The company and its members are liable to each other only to the extent they agree](https://www.legislation.gov.uk/ukpga/2002/15/section/87A), so agree in writing how the company’s own costs will be shared.

[Section 87A(8) points to rules](https://www.legislation.gov.uk/ukpga/2002/15/section/87A) that stop costs in connection with a claim being recovered through a variable service charge. One of them, [section 20J of the Landlord and Tenant Act 1985](https://www.legislation.gov.uk/ukpga/2024/22/section/64), covers a landlord’s non-litigation costs for tenants who were not members of the company.

## What has the Leasehold and Freehold Reform Act 2024 changed?

Commencement checked on 10 November 2026. The Act’s own contents list two sections under the heading [“The right to manage”](https://www.legislation.gov.uk/ukpga/2024/22/contents), sections 49 and 50. With sections 51, 52 and part of 64, they were brought into force for England and Wales on 3 March 2025 by [regulation 2 of SI 2025/131](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made). Each is in force today.

| Provision | What it changed | In force |
| --- | --- | --- |
| [Section 49](https://www.legislation.gov.uk/ukpga/2024/22/section/49) | [Raised the non-residential limit from 25 per cent to 50%, so more mixed-use buildings can qualify](https://www.legislation.gov.uk/ukpga/2024/22/section/49) | [3 March 2025](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made) |
| [Section 50](https://www.legislation.gov.uk/ukpga/2024/22/section/50) | [Replaced the rule that an RTM company pays a landlord’s costs with sections 87A and 87B, and made the company liable for the reasonable costs of complying with an information notice](https://www.legislation.gov.uk/ukpga/2024/22/section/50) | [3 March 2025](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made) |
| [Section 51](https://www.legislation.gov.uk/ukpga/2024/22/section/51) | [Moved orders to enforce obligations under the right to manage chapter from the county court to the tribunal, with enforcement in the county court](https://www.legislation.gov.uk/ukpga/2024/22/section/51) | [3 March 2025](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made) |
| [Section 52](https://www.legislation.gov.uk/ukpga/2024/22/section/52) | [Stopped first-instance applications to the High Court on matters the tribunal decides, though a challenge to a tribunal decision can still go there](https://www.legislation.gov.uk/ukpga/2024/22/section/52) | [3 March 2025](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made) |
| [Section 64, so far as it inserts section 20J](https://www.legislation.gov.uk/ukpga/2024/22/section/64) | [Stops a landlord’s non-litigation costs of a right to manage claim being counted in the variable service charge of a tenant who was not a member of the company](https://www.legislation.gov.uk/ukpga/2024/22/section/64) | [3 March 2025](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made) |

The tribunal is [the First-tier Tribunal for premises in England and a leasehold valuation tribunal for premises in Wales](https://www.legislation.gov.uk/ukpga/2002/15/section/112). This guide covers only the right to manage provisions. For the rest of the Act, including which provisions are not yet in force, see our guide to the [Leasehold and Freehold Reform Act 2024](https://instrukt.co.uk/guides/leasehold-and-freehold-reform-act-2024).

## When does it help to speak to a solicitor?

A claim has set notices, dates and tests, and a counter-notice can send it to the [tribunal](https://www.legislation.gov.uk/ukpga/2002/15/section/84). A solicitor who knows leasehold work can check the building meets the [section 72 tests](https://www.legislation.gov.uk/ukpga/2002/15/section/72), check the notices and, if there is a dispute, act for the company. Instrukt is an introducer, not a law firm. We introduce you to an independent [SRA-regulated](https://www.sra.org.uk/consumers/register/) solicitor, whom you instruct and pay directly.

## Questions

What is an RTM company?

A private company limited by guarantee whose articles state that its object, or one of its objects, is acquiring and exercising the right to manage the premises. Only one RTM company can exist for the same premises (Commonhold and Leasehold Reform Act 2002, section 73).

What is the non-residential limit for right to manage?

The right does not apply if the internal floor area of the non-residential parts exceeds 50% of the building’s internal floor area. The limit was 25% until section 49 of the Leasehold and Freehold Reform Act 2024 came into force on 3 March 2025.

Is there a resident landlord exception to right to manage?

Yes. The right does not apply to premises that have a resident landlord and contain no more than four units. Premises in a purpose-built block of flats cannot have a resident landlord for this purpose (Schedule 6, paragraph 3).

How long does a right to manage claim take?

If the landlord does not dispute it, at least four months from the date the claim notice is given: the counter-notice date is at least one month after, and the acquisition date at least three months after that. A dispute adds the tribunal’s time.

Does right to manage apply in Wales?

The 2002 Act’s right to manage provisions extend to England and Wales, and sections 49 to 52 of the 2024 Act were brought into force for both by SI 2025/131. The tribunal in Wales is a leasehold valuation tribunal. This page does not set out Welsh procedure.

## Thinking about a right to manage claim?

Tell us about the building and the leases. We introduce you to an independent SRA-regulated leasehold solicitor who can quote for an RTM claim. Instrukt is not a law firm.

[Get a solicitor’s quote](https://instrukt.co.uk/enquire/conveyancing)

**Published by Joshua Giles**, who runs Instrukt (operations). Instrukt is a trading name of JG Core Ltd and is not a law firm: it introduces clients to independent SRA-regulated solicitors and makes practice software for them. [About Instrukt](https://instrukt.co.uk/about) · [Editorial standards](https://instrukt.co.uk/editorial-standards)

## Sources

- [Commonhold and Leasehold Reform Act 2002, Part 2, Chapter 1 (right to manage)](https://www.legislation.gov.uk/ukpga/2002/15/part/2/chapter/1)
- [Commonhold and Leasehold Reform Act 2002, section 72 (premises to which the Chapter applies)](https://www.legislation.gov.uk/ukpga/2002/15/section/72)
- [Commonhold and Leasehold Reform Act 2002, section 73 (RTM companies)](https://www.legislation.gov.uk/ukpga/2002/15/section/73)
- [Commonhold and Leasehold Reform Act 2002, section 74 (membership and regulations)](https://www.legislation.gov.uk/ukpga/2002/15/section/74)
- [Commonhold and Leasehold Reform Act 2002, section 75 (qualifying tenants)](https://www.legislation.gov.uk/ukpga/2002/15/section/75)
- [Commonhold and Leasehold Reform Act 2002, section 76 (long leases)](https://www.legislation.gov.uk/ukpga/2002/15/section/76)
- [Commonhold and Leasehold Reform Act 2002, section 78 (notice inviting participation)](https://www.legislation.gov.uk/ukpga/2002/15/section/78)
- [Commonhold and Leasehold Reform Act 2002, section 79 (notice of claim)](https://www.legislation.gov.uk/ukpga/2002/15/section/79)
- [Commonhold and Leasehold Reform Act 2002, section 80 (contents of claim notice)](https://www.legislation.gov.uk/ukpga/2002/15/section/80)
- [Commonhold and Leasehold Reform Act 2002, section 81 (claim notice: supplementary)](https://www.legislation.gov.uk/ukpga/2002/15/section/81)
- [Commonhold and Leasehold Reform Act 2002, section 82 (right to obtain information)](https://www.legislation.gov.uk/ukpga/2002/15/section/82)
- [Commonhold and Leasehold Reform Act 2002, section 84 (counter-notices)](https://www.legislation.gov.uk/ukpga/2002/15/section/84)
- [Commonhold and Leasehold Reform Act 2002, section 85 (landlords not traceable)](https://www.legislation.gov.uk/ukpga/2002/15/section/85)
- [Commonhold and Leasehold Reform Act 2002, section 86 (withdrawal of claim notice)](https://www.legislation.gov.uk/ukpga/2002/15/section/86)
- [Commonhold and Leasehold Reform Act 2002, section 87 (deemed withdrawal)](https://www.legislation.gov.uk/ukpga/2002/15/section/87)
- [Commonhold and Leasehold Reform Act 2002, section 87A (costs: general)](https://www.legislation.gov.uk/ukpga/2002/15/section/87A)
- [Commonhold and Leasehold Reform Act 2002, section 87B (tribunal power to order costs where claim ceases)](https://www.legislation.gov.uk/ukpga/2002/15/section/87B)
- [Commonhold and Leasehold Reform Act 2002, section 88 (omitted 3 March 2025)](https://www.legislation.gov.uk/ukpga/2002/15/section/88)
- [Commonhold and Leasehold Reform Act 2002, section 88 as enacted (costs: general)](https://www.legislation.gov.uk/ukpga/2002/15/section/88/enacted)
- [Commonhold and Leasehold Reform Act 2002, section 90 (the acquisition date)](https://www.legislation.gov.uk/ukpga/2002/15/section/90)
- [Commonhold and Leasehold Reform Act 2002, section 92 (duties to give notice of contracts)](https://www.legislation.gov.uk/ukpga/2002/15/section/92)
- [Commonhold and Leasehold Reform Act 2002, section 94 (duty to pay accrued uncommitted service charges)](https://www.legislation.gov.uk/ukpga/2002/15/section/94)
- [Commonhold and Leasehold Reform Act 2002, section 96 (management functions under leases)](https://www.legislation.gov.uk/ukpga/2002/15/section/96)
- [Commonhold and Leasehold Reform Act 2002, section 97 (management functions: supplementary)](https://www.legislation.gov.uk/ukpga/2002/15/section/97)
- [Commonhold and Leasehold Reform Act 2002, section 112 (definitions, including the appropriate tribunal)](https://www.legislation.gov.uk/ukpga/2002/15/section/112)
- [Commonhold and Leasehold Reform Act 2002, Schedule 6 (premises excepted from right to manage)](https://www.legislation.gov.uk/ukpga/2002/15/schedule/6)
- [Leasehold and Freehold Reform Act 2024, contents (right to manage sections)](https://www.legislation.gov.uk/ukpga/2024/22/contents)
- [Leasehold and Freehold Reform Act 2024, section 49 (non-residential limit)](https://www.legislation.gov.uk/ukpga/2024/22/section/49)
- [Leasehold and Freehold Reform Act 2024, section 50 (costs of right to manage claims)](https://www.legislation.gov.uk/ukpga/2024/22/section/50)
- [Leasehold and Freehold Reform Act 2024, section 51 (compliance with obligations)](https://www.legislation.gov.uk/ukpga/2024/22/section/51)
- [Leasehold and Freehold Reform Act 2024, section 52 (no first-instance applications to the High Court)](https://www.legislation.gov.uk/ukpga/2024/22/section/52)
- [Leasehold and Freehold Reform Act 2024, section 64 (non-litigation costs, inserting section 20J)](https://www.legislation.gov.uk/ukpga/2024/22/section/64)
- [The Leasehold and Freehold Reform Act 2024 (Commencement No. 3) Regulations 2025 (SI 2025/131), regulation 2](https://www.legislation.gov.uk/uksi/2025/131/regulation/2/made)
- [GOV.UK: Right to Manage and management disputes](https://www.gov.uk/leasehold-property/right-to-manage-and-management-disputes)
- [Solicitors Regulation Authority: register of solicitors and firms](https://www.sra.org.uk/consumers/register/)

This guide is general information, not legal advice. Instrukt is not a law firm.

Related[The ban on upward-only rent reviews: what it means for your lease](https://instrukt.co.uk/guides/upward-only-rent-review-ban)[Commercial lease red flags: what to check before you sign](https://instrukt.co.uk/guides/commercial-lease-red-flags)[Break clauses in a commercial lease: how to negotiate one and use it](https://instrukt.co.uk/guides/commercial-lease-break-clause)

## Want a solicitor to handle this?

Tell us what you need and where. We'll find an independent, SRA-regulated solicitor who can quote for it.

- A reply from us within one working day
- Independent solicitors, regulated by the SRA
- Nothing is passed on until you agree

Instrukt is not a law firm. We introduce you to solicitors, who quote and act for you directly.